|
|
|
Pilot Plant Design |
Completion Date: 2009
Project Size: 15,000 man-hours
Assisted client in developing a
skid mounted pilot plant. Developed
process flow diagrams, process and
instrumentation diagrams, as well as
all equipment and instrument
specifications. Much of the
equipment and instruments were
subject to extremely low flows and
high temperature (2000º F). R&D was
responsible for developing overall
architecture for controls and power
distribution as well as detailed PLC
and SIL rated shutdown system for
reactor heating. This project also
included the detailed design of the
off-sites including utilities,
control room, raw material handling
and storage and product handling. |
 |
|
| |
|
Process
Plant Substation |
Completion Date: 2008
Project Size: $5,000,000
This project involved the
installation of a new 13.8 KV
distribution switchgear (dual source
with tie breaker) and a double-ended
480 V distribution system. Project
included a new concrete block
electrical equipment building along
with power transformers, cable tray
distribution system, structural
supports and 1100 feet of new 13.8
KV substation dual main feeders and
cable tray system. |
 |
|
| |
|
Cooling
Tower Installation |
Completion Date: 2007
Project Size: $2,000,000
R&D
was hired to provide the
specification and design for a new
cooling tower and associated
equipment that was required due to
the future increase in plant
production and required additional
cooling capacity. R&D provided the
detailed design for the concrete
cooling tower basin, pipe rack
supports, piping, pumps, filters,
electrical power and
instrumentation. |
 |
|
| |
|
Aniline Storage |
Completion Date: 2007
Project Size: $6,000,000
R&D
was requested to analyze several
locations for the purpose of
installing a one million gallon
storage tank complete with volume
containment. The tank was designed
to be supported on a concrete mat
foundation with the containment
being provided by concrete walls.
Specifications were provided for all
the supporting equipment including
exchangers, pumps, filters,
electrical power, and
instrumentation. |
 |
|
| |
|
Short Circuit
Study |
|
Completion Date: 2006
Created
an impedance one-line diagram of the
facility within a power analysis
software program. The facility
electrical equipment including
feeders, transformers, switchgears,
motor control centers, and
protective devices were modeled
based upon existing plant
documentation. The short circuit
analysis was performed in accordance
with applicable ANSI and IEEE
standards. This study included
verification of existing equipment
ratings to identify any misapplied
equipment. A protective device
coordination analysis was performed
to determine the correct settings
for the protective devices.
Coordination curves were developed
to verify and document settings.
|
 |
|
| |
|
Plant
Wide Arc Flash Study |
|
Completion Date: 2006
Plant
wide Arc-Flash Analysis was
performed in accordance with NFPA
70E and IEEE 1584 to estimate the
Arc-Flash incident energy available
at all points in the distribution
system. Arc-Flash labels were
produced which defined the approach
boundaries, flash protection
boundaries and the class of personal
protection equipment required.
|
 |
|
| |
|
Petrochemical Plant Reactor Installation |
Completion Date: 2006
Project Size: $6,000,000
This
project involved the installation of
an alloy tubed water jacketed
reactor in an existing operating
structure. The existing structure
required extensive STAAD analysis
and structural reinforcing in order
to support the additional loading
from the reactor. All supporting
pumps, filters, exchangers, piping,
electrical and instrumentation
controls were specified and
designed. |
 |
|
| |
|
Site
Drainage Modification |
Completion Date: 2006
Project Size: $5,000,000
This
was an environmentally driven
project to eliminate underground
piping for contaminated waste in
multiple process units throughout
the plant site. The underground
piping was either removed or
abandoned in place and replaced with
open trenches covered with grating.
The existing concrete sump and pumps
were replaced with a double
containment stainless steel sump
complete with a leak detection
system and new pumps with level
control. R&D personnel were
responsible for all detailed design,
hydraulics and specifications.
|
 |
|
| |
|
MDI Plant
Debottleneck |
Completion Date: 2005
Project Size: $15,000,000
The
object of this project was to
eliminate production bottlenecks
throughout the process in order to
increase production capacity. The
project was multi-faceted and
involved the replacement of several
pieces of equipment including pumps,
reactor agitators, tanks, piping,
electrical switchgear, and
instrument controls. |
 |
|
| |
|
Online Catalyst Regeneration |
Completion Date: 2004
Project Size: $8,000,000
The
purpose of this project was to
install additional piping and
instrumentation to allow one train
of a reactor section to remain
on-line while the catalyst in the
other train was being regenerated.
An increase in the production was
achieved upon the successful
completion of construction. This
project consisted of pre-turnaround
work and an ambitious shutdown
schedule.
R&D personnel were responsible for
providing the detailed design
packages to install the project in
the two phases. The detailed design
required extensive piping stress
analysis (due to the alloy steels
and high temperatures involved),
together with all electrical,
instrumentation, and demolition
work. |
 |
|
| |
|
HCL
Storage & Loading |
Completion Date: 2003
Project Size: $15,000,000
R&D’s
responsibilities included site
selection and resolving
environmental issues to the
satisfaction of the plant
environmental department. The
project consisted of the detailed
design and specifications required
to install two (2) rubber lined
storage tanks, an HCL railcar
loading rack, piping to and from the
storage tanks, two (2) loading
pumps, new pipe racks, a vent
scrubber together with all
electrical and instrumentation. |
 |
|
| |
|
Alternate Fuels for Cogen Units |
Completion Date: 2002
Project Size: $15,000,000
This
project involved converting existing
natural gas fueled generators to run
on acetylene off gas. R&D personnel
were responsible for coordinating
with Cogen Supplier to ensure smooth
transition. Project included all
structural, piping, electrical, and
instrumentation required to convert
three Cogen units. |
 |
|
| |
|
Micro
Herbicide Unit |
Completion Date: 2001
Project Size: 12,000 man-hours
R&D
provided front end process design
and detailed engineering for the
installation of a new product in the
existing unit. The scope of the
project included new storage tanks,
reactor, pumps, product weighing
scales, bag unloader and revamping
the product vacuum system.
Included were scope books, expansion
of their DCS system along with
civil, mechanical, and
instrument/electrical detailed
design. |
 |
|
| |
|
Microencapsulation Unit |
Completion Date: 2000
Project Size: $3,000,000
R&D
personnel were responsible for the
development of the PFD’s and P&ID’s
for this solids handling project.
Upon completion of the front end
process development the detailed
design began and included reactor
specifications, storage tank
specifications, pump specifications,
truck and rail car loading racks, a
new pipe rack and reactor supporting
structure.
The
detailed design included all
foundations, structure, piping,
electrical power and instrumentation
required to complete the
installation. |
 |
|
| |
|
MDI Pures & Variants Expansion |
Completion Date: 2000
Project Size: $20,000,000
R&D’s
scope was to provide design and
construction drawings that were
issued in two (2) individual
construction packages. Each package
involved a multi-discipline effort
including piping, civil/structural,
and instrumentation, electrical and
mechanical. The majority of the work
involved the installation of three
(3) product storage tanks, new
reactor pumps, exchangers, filters a
truck loading facility, concrete
structure for elevated reactor, and
load cells for filling. |
 |
|
| |
|
Insecticide Unit |
Completion Date: 1999
Project Size: $6,000,000
This
project involved the installation of
a new Insecticide Unit in an
abandoned steel structure. This
project took advantage of using
existing storage tanks and vessels
for raw materials and product. This
project installed three (3) new
agitated process vessels equipped
with half-pipe heating and cooling
jackets along with one (1) new main
reactor equipped with disperser and
agitator, as well as half-pipe
heating and cooling jacket. Project
involved structure rework, solids
handling, drum heating and
dispensing, transfer pumps, heat
exchangers, filters, tank farm
storage, rail and truck loading.
Process was completely batch
controlled by a new Yokogawa DCS
system. |
 |
|
| |
|
MDI-1 Refrigeration Compressors |
Completion Date: 1998
Project Size: $8,000,000
This
project consisted of upgrading two
(2) existing centrifugal
compressors, changing process from
Freon refrigerant to KLEA 123a
refrigerant, installing larger 2,250
HP motor and larger gear box, and
redesigning foundation to alleviate
vibration and downtime. Compressor
ran at 6,400 RPM with an outlet
pressure of 180 psig. |
 |
|
| |
|
Plant
Wide Structure Review |
|
Completion Date: 2007
This
project involved the following:
Identification of all vessels and
pipelines containing material which
would endanger the plant, plant
personnel or the public in the event
of a spill. We identified all
structural framing in buildings and
pipe racks which supported the
hazardous equipment. Drawings were
prepared locating and registering
all such structural framing members.
All identified structural framing
members were inspected and reports
were written indicating their
condition and any required repairs.
Upon the completion of the
inspection phase a system of
periodic re-inspections was
established to insure that all
critical structures are properly
maintained. Upon completion of this
project, R & D Consulting was
designated as the Responsible
Engineer for the Structural
Integrity of their plant. |
 |
|
| |
|
Offsite Pipe Racks & Utilities Upgrade |
Completion Date: 1996
Project Size: $5,000,000
This
project consisted of the design of a
major three tier pipe rack running
from one end of the plant to the
other, together with pump upgrades
to the process water facility and
the design of new process water
header, steam line and nitric acid
line. The project included all
electrical and instrumentation
required to install the project. |
 |
|
| |
|
Herbicide
Unit Reactor |
Completion Date: 1996
Project Size: $3,500,000
This
project consisted of the
installation of a new reactor,
agitators, transfer and cooling
pumps and a bulk bag unloader. The
project involved the modification
and strengthening of the existing
structure. The process was
completely automated and interfaced
with Johnson/Yokogawa DCS. |
 |
|
| |
|
MDI
Pures & Variants Expansion |
Completion Date: 1996
Project Size: $20,000,000
R&D’s
scope was to provide design and
construction drawings that were
issued in two (2) individual
construction packages. Each package
involved a multi-discipline effort
including piping, civil/structural,
and instrumentation, electrical and
mechanical. The majority of the work
involved the installation of three
(3) product storage tanks, new
reactor pumps, exchangers, filters a
truck loading facility, concrete
structure for elevated reactor, and
load cells for filling. |
 |
|
| |
|
New
Metals Process Facility |
Completion Date: 1995
Project Size: $8,000,000
R&D's
responsibilities included equipment
arrangement, underground leak
detection system, design and
installation documents for major
equipment including towers, screens,
pumps, exchangers, reactors and
railcar loading facilities. |
 |
|
| |
|
Tabular Crushing Modifications |
Completion Date: 1993
Project Size: $6,000,000
R&D’s
responsibilities included equipment
arrangement design, equipment
specifications for major equipment
including tri-deck vibrating
screens, crushers, duct work, dust
collection system, railroad loading
facilities, conveyors and all
supporting structures. Electrical
and instrumentation included design,
specifications and purchase
requisitions for all equipment
including PLC interlock control
systems. |
 |
|
| |
|
Spent
Acid Recovery Unit |
Completion Date: 1991
Project Size: $10,000,000
This
project consisted of the design of a
six (6) level structure, design and
specification for a vertically
mounted air condenser, glass lined
columns, heat exchangers, pumps,
filters and stress analysis for the
complete piping system. The
electrical and instrumentation
effort included the design and
specifications for all equipment and
PLC control systems. |
 |
|
|
© 2009 R&D
Consulting. All rights reserved.
|